On 15 March 2015, Sasol and Murray & Roberts concluded an NEC3 Engineering and Construction Contract for work at Sasol's Secunda plant. The contract was a time charge contract providing for a project manager to assess payments and a dispute resolution process involving adjudication followed by arbitration. Due to budget constraints, in March 2017 the project manager issued PMC200 instructing Murray & Roberts to demobilise resources and began deducting costs from payment applications, resulting in approximately R42 million in deductions. Murray & Roberts disputed these deductions (Disputes 1 and 2) which the adjudicator initially upheld. Murray & Roberts then referred Disputes 1 and 2 to arbitration. While the arbitration was pending, the project manager continued applying PMC200 to subsequent payment applications (Disputes 3, 5, 6, 8-12), which the adjudicator also upheld. On 9 October 2018, the arbitrator ruled in favour of Murray & Roberts, finding that PMC200 was not contractually binding and that timesheets submitted by Murray & Roberts were contractually binding. When Murray & Roberts requested the project manager to implement the award across all 10 disputes, he did so only partially on Sasol's instruction. Murray & Roberts then referred Dispute 16 to the adjudicator, challenging the project manager's refusal to apply the arbitrator's principles to payment advice 38. The adjudicator found in favour of Murray & Roberts on 12 May 2019, ordering payment. Sasol refused to comply, arguing the adjudicator's decision was invalid.