In May 1994, Hippo Valley Estates Limited (Hippo) entered into a construction contract with Main Contracting (Private) Limited (Main) for the construction of Mteri Dam in Chiredzi District. The contract had strict completion deadlines: the retaining wall to store water by 1 October 1995, water release into the canal by 31 January 1996, and full completion by 31 May 1996. Hart Frost was the consulting engineer. After work commenced, numerous site meetings raised concerns about the slow rate of progress. On 15 June 1995, the engineer certified in writing to Hippo that Main had failed to proceed with due diligence and was not executing works in accordance with the contract. Based on this certification under clause 65(1), Hippo gave seven days' notice and terminated the contract. Main disputed the validity of termination, arguing that notice under clause 46 regarding slow progress should have been given first and that the engineer had an ulterior motive related to his failure to designate areas with sufficient core material. The matter went to arbitration before Terrence Colin Kabell (the arbitrator), who found the termination valid. Main's liquidator (the appellant) applied to the High Court to set aside the arbitral award on grounds it was contrary to public policy. The High Court dismissed the application, and the appellant appealed to the Supreme Court.