The appellant, Tubestone (Pty) Ltd, imports tyres. It subscribed to an integrated industry waste tyre management plan (WTM plan) administered by the respondent, the Recycling & Economic Development Initiative of SA NPC (Redisa). The plan was promulgated on 30 November 2012 under the National Environmental Management Waste Act and required tyre producers to pay a waste tyre management fee. The fee was set at R2.30 per kilogram and was to be reviewed annually. Tubestone paid the fees for four years but stopped paying between October 2016 and January 2017. Redisa launched proceedings to recover R2,479,335 in arrear levies. In response, Tubestone raised collateral challenges, alleging that Redisa failed to review the fee annually as required, making the fees unlawful. The court had to consider whether Tubestone's delay in raising these challenges should prevent them from being entertained.
The appeal was dismissed with costs, including the costs of two counsel where employed.
In collateral challenge matters, delay is a factor that must be considered. A court must evaluate whether the challenger had a sufficient opportunity to contest the administrative act directly but failed to do so. The correct test is whether the administrative act was directed specifically at the challenger or was of general application, and whether the challenger knew of it and had an opportunity to challenge it. A collateral challenge will not automatically succeed merely because it is described as 'classical'; in all cases, the court must consider all relevant circumstances including delay, the explanation for it, and any prejudice.
The court suggested that the formalistic distinction between 'classical' and 'extended' collateral challenges should be jettisoned in favour of treating collateral challenges as a single genus, with delay always being a potential factor to consider depending on the circumstances.
This case clarifies the role of delay in collateral challenges in South African administrative law. It interprets the Constitutional Court's judgment in Merafong and holds that delay is not irrelevant in so-called 'classical' collateral challenges by private parties. It provides a unified framework for evaluating collateral challenges regardless of whether they are brought by private persons or organs of state, focusing on whether the challenger had a sufficient opportunity to challenge the administrative act directly.