The applicant, a body corporate of the Tradewinds Sectional Title Scheme, sought relief against the third respondent's construction of earthworks (a peninsula) on the bank of the Hartebeespoort Dam. The third respondent was developing a golfing estate and began construction of the peninsula in April 1999. Following a complaint from the applicant, the Department of Agriculture, Conservation and Environment (DACE) issued a directive under s 28 of NEMA requiring the third respondent to cease works and submit an environmental impact assessment. The third respondent complied and applied for authorisation. On 3 April 2001, the second respondent granted authorisation in terms of s 22 of the Environment Conservation Act 73 of 1989 (ECA) for the completion of the peninsula. The applicant appealed this decision to the first respondent, but the appeal was dismissed. The peninsula was then completed. The applicant challenged the decisions as unlawful, arguing that s 22 of ECA did not permit retrospective authorisation of works already partially undertaken. Prior to this application, another entity (Biz Afrika 775) had brought similar proceedings which were settled in February 2001, with the settlement including an undertaking not to interfere with the environmental impact process relating to the Pecanwood Estate Development.
Application dismissed with costs, including costs of two counsel.
The ratio decidendi of the case includes several binding principles: (1) Section 32(1) of NEMA confers locus standi in iudicio on bodies corporate established under the Sectional Titles Act to bring environmental proceedings, beyond the limited standing granted in s 36(6) of the Sectional Titles Act. A body corporate is a "person" for purposes of s 32(1) of NEMA. (2) The phrase "any person" in s 32(1) of NEMA is of wide and unrestricted import, and should be given a broad interpretation in environmental cases to ensure constitutional environmental rights enjoy full protection. (3) Government Notice R1182, as amended by R1355, does not apply to activities that were "commenced with" before the specified commencement date. Where construction forms an integral part of an entire project that commenced before the commencement date, the entire project (including later phases) is exempt from R1182. (4) Section 22 of the Environment Conservation Act does not prohibit ex post facto authorisation for the completion of a partially undertaken activity, provided the authorisation properly complies with environmental legislation and protection objectives. The completion of a partially undertaken activity can constitute the "proposed activity" for purposes of authorisation. (5) Courts will not grant declaratory relief that is merely academic or lacks practical significance. Relief must result in tangible consequences beyond a mere legal opinion. (6) Where the same persons use different legal entities to pursue substantially the same relief on the same grounds, courts will pierce the corporate veil and hold the parties bound by earlier settlement agreements, particularly where those agreements were reached for consideration. (7) In motion proceedings, all necessary allegations upon which an applicant relies, including those according it locus standi, must appear in the founding affidavit. New grounds cannot be introduced in replying affidavits.
Several obiter statements are noteworthy: (1) The court noted that environmental considerations must be accorded appropriate recognition and respect in administrative processes, citing the constitutional inclusion of environmental rights as fundamental justiciable human rights and the need for a change in legal and administrative approaches to environmental concerns. (2) The court observed that a court retains discretion to refuse declaratory relief even where a justiciable dispute exists, if granting relief would serve no practical benefit. (3) The court suggested that while s 32(2) of NEMA allows courts to decline to award costs against unsuccessful environmental litigants who act reasonably out of concern for the public interest, this discretion will not be exercised where the applicant has other motives beyond environmental protection (such as protecting property values or views). (4) The court indicated that had it been necessary to decide, it would have found that the third respondent's existing authority from DWAF did not constitute "vested rights" that removed the activity from the ambit of R1182, though this was not ultimately determinative. (5) The court noted that settlement agreements that include undertakings not to interfere with environmental processes should not be considered contra bonos mores, particularly where entered into for consideration. (6) The court observed that courts should facilitate the reception of further affidavits to cure deficiencies in proof of authority where founding papers contain allegations of authority, to prevent the rules of practice from holding unjustifiable sway over substantive justice.
This case is significant for several aspects of South African environmental and administrative law: (1) It confirmed that bodies corporate have locus standi to bring environmental proceedings under s 32(1) of NEMA, which extends beyond the limited locus standi granted in s 36(6) of the Sectional Titles Act. The court adopted a broad interpretation of standing in environmental cases, consistent with constitutional environmental rights. (2) It established that environmental legislation does not absolutely prohibit ex post facto authorisation of partially completed activities, provided the authorisation process properly addresses environmental concerns and complies with the spirit and objectives of the legislation. This provides flexibility in environmental regulation while maintaining environmental protection. (3) It illustrates the principle that courts will not grant declaratory relief that is merely academic or does not result in practical consequences. Relief must have tangible significance. (4) It demonstrates the application of the doctrine of legality in the environmental context and the ultra vires principle in relation to administrative decisions. (5) It shows how courts will "pierce the corporate veil" to prevent abuse of separate legal personality where different entities are used by the same persons to pursue substantially the same relief after settling earlier litigation. (6) The case also clarifies procedural requirements in motion proceedings, including that founding papers must establish all necessary elements including locus standi, and that new grounds cannot generally be introduced in replying affidavits.