CaseNotes LogoCaseNotes
  • Home
  • Library
  • Research
  • Discussion Hub
  • Wiki
  • Latin Dictionary
  • Question Bank
  • Settings
S

Student

Student Account

South African Law • Jurisdictional Corpus
HomeLibraryResearchQuestionsSettings
Judicial Precedent
Ask AI

Roads Agency Limpopo (Pty) Ltd v Murray and Roberts Construction (Pty) Ltd and others

Citation(496/08) [2009] ZASCA 128 (29 September 2009)
JurisdictionZA
Area of Law
Contract LawConstruction Law
Free account

Get the most out of this judgment

Create a free CaseNotes account to save this case, see how it's cited, get an AI summary, and search 10,000+ SA judgments.

Create free accountor sign in
Engineering Contract Law

Facts of the Case

The appellant (RAL) engaged the first respondent (contractor) under a COLTO standard form engineering contract to construct roadworks in the Phiphidi area during July 2005. Work was halted for approximately five months (October 2005 to April 2006) due to an interim interdict obtained by an unsuccessful tenderer, Raubex (Pty) Ltd, pending a review application. Raubex gave an undertaking to indemnify the contractor for losses arising from the delay. The contractor claimed additional remuneration for expenses incurred during the work stoppage under clause 51(1) of the contract, which the engineer awarded. RAL rejected interim payment certificate No. 10 (issued 13 October 2006) because it included the work stoppage claim, taking the view that Raubex should pay this amount under its indemnity. RAL instructed the engineer to issue a fresh certificate excluding this amount. Certificate No. 11 was also rejected for incorrect calculations. The contractor issued notice on 15 November 2006 demanding payment of certificate 10 within 14 days, threatening cancellation. On 13 December 2006, the contractor purported to cancel the contract for non-payment. RAL accepted the cancellation on 15 December 2006. The engineer subsequently issued payment certificate 12/13 covering the period to cancellation, which was also disputed. Amended certificates 10 and 11 for lesser amounts were issued and paid. The contractor applied for judgment on the original amounts in certificates 10, 11 and 12/13.

Legal Issues

  • Whether the employer (RAL) had the right under clause 2(8) of the contract to reject and reverse interim payment certificates issued by the engineer
  • Whether the employer properly exercised its power under clause 2(8) when it instructed the engineer to amend certificates rather than issuing new certificates itself
  • Whether the employer's power to reverse certificates under clause 2(8) extended to certificates embodying the engineer's ruling under clause 51
  • Whether the contractor was entitled to rely on clause 59 (cancellation by contractor) and claim payment under certificate 12/13 issued after cancellation of the contract
  • Whether the cancellation of the contract was effected under clause 59 such that the contractor's claims survived cancellation

Judicial Outcome

The appeal succeeded with costs (including costs of two counsel). The order of the High Court (Southwood J) was set aside. The contractor's application was dismissed with costs (including costs of two counsel).

Ratio Decidendi

The binding legal principles established are: (1) Under clause 2(8) of the COLTO contract, the employer has the power to reverse (revoke or annul) any certificate issued by the engineer, and if deemed necessary, to amend it, with such amended certificate deemed to be issued by the engineer. (2) The manner in which the reversal is effected (whether the employer issues a new certificate itself or instructs the engineer to recalculate) does not affect the validity of the exercise of the power under clause 2(8). (3) The power to reverse certificates under a clause beginning "Notwithstanding any provisions to the contrary in the Contract" and referring to "any certificate" extends to all certificates, including those embodying the engineer's rulings under claims provisions (such as clause 51), unless expressly limited. (4) A certificate issued after cancellation of the contract is not a certificate contemplated by the contract while in force. (5) Where a contractor purports to cancel a contract under a specific contractual provision (clause 59) for employer's default, but the employer was not in fact in default and accepts the contractor's conduct as repudiation, the cancellation is not effected under that contractual provision and the contractor cannot rely on survival clauses attached to that provision. (6) The contractor is not without remedy where the employer reverses certificates, as dispute resolution provisions in the contract (clauses 60 and 61) provide mechanisms for resolution.

Obiter Dicta

The court noted that clause 2(8) is a "novel clause in the field of building and engineering contracts" and represents a departure from earlier forms of standard contracts which bound the employer to pay interim certificates while the contract remained in force, with disagreements deferred for resolution after completion. The court emphasized that each contract must be construed according to its own terms and not those of other "standard contracts". The court also observed (without deciding) that the fact that an interim certificate creates a self-sufficient debt does not mean that the employer cannot raise a defence to a claim based on such a certificate, accepting for the purposes of the case that the employer is entitled to raise a defence of any kind to claims based on certificates. The court did not need to determine the ultimate validity of the contractor's claim for work stoppage expenses or whether Raubex or RAL would ultimately be liable for such expenses under the indemnity undertaking.

Legal Significance

This case establishes important principles regarding the interpretation and operation of COLTO standard form engineering contracts in South African law, particularly concerning: (1) the scope of an employer's power to reject interim payment certificates under clause 2(8); (2) the proper interpretation of "reverse" in such clauses as meaning to revoke or annul; (3) the relationship between the employer's power to reverse certificates and the engineer's rulings under claims provisions; and (4) the distinction between contractual cancellation provisions and common law cancellation/repudiation. The judgment clarifies that interim payment certificates under standard form contracts do not create absolute payment obligations immune from employer challenge where the contract expressly confers such powers on the employer. It represents a departure from earlier standard contract forms that bound employers to pay interim certificates while the contract remained in force.

Cases Cited in This Judgment

  • Masstores (Pty) Ltd v Murray & Roberts Construction (Pty) Ltd(573/2007) [2008] ZASCA 94 (12 September 2008)
    Appeal From

    The Supreme Court of Appeal (Streicher, Nugent, Lewis, Bosielo JJA and Hurt AJA) allowed the appeal with costs. The court held that the employer had properly…

Practice This Case

Sign up to practise IRAC analysis, issue spotting, and argument building on this case.

Explore More Cases

More Contract Law cases

  • (1) Douglas Tanyanyiwa (2) Douglas Warriors Football Club v Lawrence Bernard GwaradaCivil Appeal No. SC 150/11; Judgment No. SC 79/2014
  • (1) Elias Hwenga (2) Mercy Hwenga (3) Kenneth (4) Prince Nyemba (5) A. P. Phillip and Company (Private) Limited v FBC Bank LimitedJudgment No. SC 36/21, Civil Appeal No. SC 204/16
  • 68 Wolmarans Street Johannesburg (Pty) Ltd and Others v Tufh Limited(1263/2022) [2024] ZASCA 48 (15 April 2024)
  • A A Alloy Foundry (Pty) Limited v Titaco Projects (Pty) LimitedCase No. 309/97
  • A. Adam and Company (Private) Limited and Others v Goodliving Real Estate (Private) LimitedSC 18/21; Civil Appeal No. SC 444/19
  • Aaron Chitewe v Josiah ChiroodzaJudgment No. SC 70/2002, Civil Appeal No. 391/00
  • Aaron Majero v Dubekile DandaHH 119-18, CIV 'A' 311/08
  • Aaron Mwenje v Intermarket Building SocietySC. 80/05 (Civil Appeal No. 358/04)

More South Africa cases

  • 3M South Africa (Pty) Ltd v The Commissioner for the South African Revenue Service(272/09) [2010] ZASCA 20 (23 March 2010)
  • 4 Seasons Logistics CC v Kgotse(1215/2023) [2026] ZASCA 09 (04 February 2026)
  • 4 Seasons Logistics CC v Nicholas Ngwanammoto Kgotse(1215/2023) [2026] ZASCA 09 (4 February 2026)
  • 4-Tune Investments (Pty) Ltd v Kingsgate Body CorporateCSOS 4565/WC/22 (Adjudication Order, 29 November 2023)
  • 68 Wolmarans Street Johannesburg (Pty) Ltd and Others v Tufh Limited(1263/2022) [2024] ZASCA 48 (15 April 2024)
  • 9 on Rydal Vale Court Body Corporate v Pan African Holdings Pty LtdCSOS-4563/KZN/23 (Adjudication Order, 8 November 2023)
  • AAA Investments (Proprietary) Limited v The Micro Finance Regulatory Council and Another
2006 (11) BCLR 1255 (CC) (also reported as CCT 51/05)
  • A A Alloy Foundry (Pty) Limited v Titaco Projects (Pty) LimitedCase No. 309/97