In 2007, Oudtshoorn Municipality awarded a tender for construction of 663 houses to Silver Buckle Trade (Pty) Ltd t/a Yethu Projects (Yethu). Yethu obtained bridging finance from Nurcha Finance Company and ceded to Nurcha all payments payable by the municipality in respect of the project. The municipality gave a written undertaking to Nurcha irrevocably and unconditionally undertaking to pay all moneys due and payable to Yethu into a nominated project account exclusively. The municipality appointed Arcus Gibb as project managers who, together with the municipality's building control officer, would certify completed work through payment certificates. Nurcha relied on these certificates in allowing further loan advances to Yethu. During October 2007 to August 2009, Arcus Gibb certified 39 payment certificates. The municipality paid 36 certificates into the project account but failed to pay three certificates (numbers 7, 8 and 20) into the project account, instead paying them into a different account held by Yethu. The amounts not paid into the project account were R1,493,638.90, R2,086,204.10 and R635,076.49. Yethu subsequently failed to complete the project and the municipality cancelled the building contract with Yethu. Yethu was placed under final liquidation on 14 April 2010. The municipality appointed another contractor to complete the project.