The respondent (Enviroserve) operated a waste disposal site in Port Elizabeth and engaged the appellant (Hawkins) as consulting engineers to design a second waste disposal pit (Aloes II), manage the tender process, and administer and supervise construction. After tenders were invited, the tender was awarded to a joint venture contractor. The construction contract incorporated the General Conditions of Contract for Works of Civil Engineering Construction, 6th edition (1990) (GCC). The contractor tendered a 'through rate' for excavation rather than separate rates for different material types. During construction, a variation order was issued requiring excavation an additional three meters beyond the original 30-meter depth. The contractor encountered unexpectedly hard rock (hard mudstone) requiring drilling and blasting, which significantly slowed progress. On 5 September 1997, the appellant (engineer) wrote expressing concern about delays. The contractor responded on 8 September 1997, explaining the delays and stating in the final paragraph that it planned to blast approximately 103,000 cubic meters of hard shale. On 19 and 22 September 1997, the contractor wrote further letters, the latter expressly invoking clauses 39, 40 and 50 of the GCC and claiming additional cost and time. The engineer rejected the claim on the basis that no extra payment was required given the tendered rates. The dispute went to arbitration, where the arbitrator held that the 8 September letter constituted proper notice under clause 50(1) of the GCC and awarded the contractor R1,475,865. Enviroserve then sued Hawkins for damages, claiming breach of contract for failing to recognize the 8 September letter as proper notice. The trial court (Sandi J) found for Hawkins, but the Full Court reversed. Hawkins appealed to the Supreme Court of Appeal.