Eskom held a perpetual servitude registered in 1958 (No. 344/1958) over property at 83 Blue Hills Extension 9, Gauteng, for conveying electricity by means of cables and wires. The servitude deed required Eskom to pay annual rental (£15) to the registered owner, with clause 3 providing for cancellation if payment was in arrear for one month after 30 days' written notice. Clause 9 required new owners to produce their title deed to Eskom upon transfer, entitling Eskom to treat the transferor as owner until production. Ms Norton acquired the property from Mr Ronald King on 23 July 2010. Norton did not produce her title deed as required by clause 9. However, on 8 October 2010, Eskom's attorneys wrote to Norton acknowledging her ownership and offering to capitalize the annual rental. Norton did not respond. Eskom failed to pay rental to Norton and instead paid the original owners (Krause Family Trust) on 20 July 2011. On 30 April 2012, Norton gave notice of intention to cancel the servitude due to non-payment. Eskom failed to pay within the 30-day period. On 5 June 2012, Norton cancelled the notarial agreement. Eskom then tendered payment of R5.63 arrears, which Norton rejected. Norton applied to the North Gauteng High Court for a declaration that the servitude was cancelled.