JVE Civil Engineers Inc (JVE) provided engineering services to Blue Bantry Investments 235 (Pty) Ltd (Blue Bantry) in relation to a residential property development at Groot Phesantekraal, Durbanville, Western Cape. JVE sued Blue Bantry for fees arising from engineering services rendered during Phase 3 of the development. During litigation, the parties agreed to arbitration in August 2018 and agreed that high court pleadings would stand as pleadings in arbitration. The dispute concerned two main fee claims: (1) the BICL claim - an additional 20% fee under clause 6 of the JVE1 agreement (May 2008) relating to Bulk Infrastructure Contribution Levies; and (2) the 1.25 multiplication factor claim for alterations to existing work under ECSA tariffs. Blue Bantry pleaded in paragraph 8.2.4 of its amended plea (in answer to a damages claim) that a subsequent oral agreement was concluded between August-September 2009 whereby Blue Bantry would pay these amounts only if and when they were recovered from the City of Cape Town, which Mr van Eeden agreed to. JVE was unsuccessful before the first arbitrator and before the appeal arbitrator (retired Judge Fourie) who dismissed the appeal on 12 December 2019. The appeal arbitrator found that the Service Agreement 2008 between Blue Bantry and the City of Cape Town had amended the JVE1 agreement, and that the oral agreement in paragraph 8.2.4 had been proved and admitted by Mr van Eeden, making the claims premature as the amounts had not been recovered from the City.
The appeal was dismissed with costs, including the costs of two counsel.
An arbitrator exceeds his powers by deciding claims on grounds not pleaded, as the arbitrator's powers derive solely from the arbitration agreement and are limited to matters pleaded. However, where a defence constitutes a complete answer to claims (such as a compromise agreement), it would be artificial and unjust to disregard that defence merely because it was not pleaded specifically in answer to those particular claims, provided it was pleaded elsewhere and proved. In such circumstances, no gross irregularity within the meaning of section 33(1)(b) of the Arbitration Act 42 of 1965 occurs, as the parties were afforded a fair hearing. The determinative question is not technical compliance with pleading rules but whether the arbitrator misconceived the nature of the inquiry or denied the parties a fair hearing. Where the substance of a complete defence was pleaded, led in evidence, and established without prejudice to any party, the dismissal of claims on that basis does not constitute a reviewable irregularity merely because of the precise location of the pleading.
The court reiterated established principles regarding review of arbitration awards, citing Telcordia Technologies Inc v Telkom SA Ltd for the proposition that "an arbitrator 'has the right to be wrong' on the merits of the case" and that errors in interpretation of agreements, application of law, or evaluation of evidence do not constitute misconception of the nature of the inquiry. The court also cited Palabora Copper (Pty) Ltd v Motlokwa Transport & Construction (Pty) Ltd to emphasize that "where an arbitrator engages in the correct enquiry, but errs either on the facts or the law, that is not an irregularity and is not a basis for setting aside an award" and that "[i]f the parties choose arbitration, courts endeavour to uphold their choice and do not lightly disturb it." The court noted that it is possible for parties in arbitration to amend the terms of reference by agreement, even tacitly or by conduct. The court observed that the appeal arbitrator did not apply his mind to whether the condition in clause 6 of the JVE1 agreement had been fulfilled as alleged, having determined the claim on the basis of the unpleaded amendment by the Service Agreement 2008, but this did not ultimately affect the outcome given the compromise defence.
This case clarifies the scope of review of arbitration awards under section 33(1)(b) of the Arbitration Act 42 of 1965, particularly in relation to pleadings and the boundaries of an arbitrator's powers. It establishes that while arbitrators are confined to matters pleaded and cannot decide unpleaded issues, courts will adopt a substantive and practical approach when a pleaded defence constitutes a complete answer to a claim, even if not specifically pleaded in answer to that particular claim. The case reinforces the principle that courts will not lightly interfere with arbitration awards and will uphold parties' choice of arbitration. It demonstrates that a technical pleading deficiency will not necessarily constitute a gross irregularity justifying review where the substance of the defence was pleaded, proved, and did not result in unfairness to the parties. The judgment balances the strict rule that arbitrators cannot exceed their pleaded mandate with the principle that procedural technicalities should not trump substantive justice where no prejudice results. The case also confirms that section 33 of the Arbitration Act applies equally to appeal arbitration awards, and that if such an award is set aside, the matter must be submitted to a new arbitration tribunal under section 33(4).
Explore 1 related case • Click to navigate