Samancor Ltd (plaintiff/respondent) instituted action as cessionary of claims originally belonging to its subsidiary, Samancor Chrome Ltd (the employer). Two contracts were concluded in late 1989 for construction of a water pipeline at Steelpoort: (1) a construction contract in November 1989 between the employer and a party identified as "Cocciante Construction"; and (2) a professional services contract in December 1989 between the plaintiff (acting for the employer) and Van Immerzeel & Pohl (the engineer) for supervision of construction. The work was performed by Cocciante and Borsei Civil Construction CC, with construction commencing January 1990 and certified complete on 27 November 1990. On 24 January 1991, the pipeline was discovered to be leaking due to corrosion caused by sub-standard coating and lining of pipes and ineffective cathodic protection system. The pipeline required replacement. The employer paid R1,377,024.50 to the contractor pursuant to payment certificates issued by the engineer. On 28 June 1991, the employer sold its business to the plaintiff, including debts. A further cession agreement was executed on 30 September 1993. Summons was issued in November 1993 against Cocciante Construction CC and the engineer. The firm Cocciante Construction (second appellant) was later joined as third defendant.
The appeals of both appellants were dismissed with costs, including costs of two counsel. The trial court's order was altered by: (1) substituting R910,570 for R973,544.48 in paragraph 1 (judgment against the engineer); and (2) substituting R1,145,559 for R1,208,533.48 in paragraphs 2 and 3 (judgment against the firm and maximum total recovery). These substitutions reflected the deduction of R62,974 in retention moneys from both awards.
The binding legal principles established are: (1) The identity of parties to a contract must be determined from the contract read as a whole and background circumstances existing at the time of contracting, with the contract's express identification being the starting point. (2) Under section 12(3) of the Prescription Act 68 of 1969, prescription does not commence until the creditor has knowledge (actual or constructive through reasonable care) of the debtor's identity; where the creditor reasonably believes a different entity is the debtor based on representations and conduct, the creditor cannot be held to have constructive knowledge of the true debtor's identity. (3) An engineer's duty to supervise construction includes examining materials and workmanship for compliance with specifications, including quality, proper preparation, and installation in accordance with contract requirements. (4) Where two parties independently breach separate contracts (construction contract and supervision contract) causing the same or overlapping damage to the plaintiff, both are liable concurrently/severally for that damage; the plaintiff may sue either or both without being required to pursue one before the other, though the plaintiff cannot recover the same damages twice. This is independent concurrent liability, not joint liability. (5) A contractor is liable for defective work by nominated sub-contractors under clause 61 of the General Conditions of Contract unless the contractor properly objected or required the sub-contractor to enter a compliant sub-contract with indemnity provisions. (6) Under construction contracts providing for rectification at contractor's cost or employer's right to re-execute and claim reimbursement (clause 49), the employer may claim damages equivalent to re-execution costs even if not the landowner, as the contractual right to reimbursement constitutes a money claim rather than requiring specific performance. (7) Retention moneys held by the employer under a construction contract must be deducted from damages awarded for defective work.
The Court made several non-binding observations: (1) The ISEP Structural Engineering case (holding that South African law does not recognize damages as an alternative to specific performance) has been subject to severe criticism, though the Court found it unnecessary to determine the correctness of that criticism as the case was distinguishable. (2) The Court noted with apparent approval the English law position on concurrent liability in construction cases as set out in Hudson's Building and Engineering Contracts, observing that concurrent liability of contractor and engineer for the same damage is a "classic example" where causes of action are "separate and independent" with potentially different measures of damage. (3) The Court observed that the use of "Direkteur" (director) when signing a contract does not necessarily indicate a legal person is contracting, as the word can mean "superintendent, manager" in contexts not involving corporations. (4) The Court noted that if the parties intended to transfer all assets of the employer to the plaintiff, it would be "inherently unlikely" they would intend the employer to retain only damage claims while transferring everything else. (5) The Court questioned whether there was any evidence of what the engineer actually did by way of supervision, noting "no answer was forthcoming" when counsel was asked, which "comes as no surprise in the case of an engineer whose first line of defence was that his duties of supervision were of a most attenuated kind." (6) The Court referred to the Nedcor Bank v Lloyd-Gray Lithographers case as authority for similar principles of concurrent liability in delict.
This case is significant in South African construction and contract law for establishing important principles regarding: (1) the identification of contracting parties where informal business structures are used; (2) the commencement of prescription where knowledge of debtor identity is unclear; (3) the scope of engineers' supervisory duties under professional services contracts; (4) the doctrine of concurrent or independent liability where two parties breach separate but interconnected contracts causing overlapping damage; (5) the right to claim damages for breach of construction contract even where the employer is not the landowner; and (6) contractor liability for nominated sub-contractors' defective work. The case clarifies that a plaintiff suffering damage from breaches of two separate contracts by different parties may sue either or both defendants without being required to exhaust remedies against one before proceeding against the other, though double recovery is prohibited. This represents an adoption of principles similar to English law on concurrent liability in construction disputes.
Explore 1 related case • Click to navigate