The plaintiff, Timothy Curtis Jackson, was a commercial farmer leasing Ruya Ranch Farm for tobacco and maize production. He entered into a contract with the defendant (Zimbabwe National Water Authority - ZINWA) for the supply of 250 megalitres of raw water per year from Amanda Dam in Mt Darwin for irrigation purposes. The plaintiff cultivated 90 hectares of tobacco based on this agreement. When the plaintiff attempted to abstract water from Amanda Dam as provided in the contract, he was prevented from doing so by A1 resettled farmers who claimed the water level was too low and would not leave adequate water for their livestock. Despite several meetings with ZINWA officials and government officials to resolve the issue, no breakthrough was achieved. As a result of the lack of water, the plaintiff's tobacco crop failed. The plaintiff claimed damages of US$4,371,000 for the loss of his crop. The contract contained clause 3 (availability of water not guaranteed) and clause 19 (ZINWA not responsible for loss or damage from failure to supply water except for willful acts or negligence of staff).
The application for absolution from the instance at the close of the plaintiff's case was granted in favor of the defendant with costs. The plaintiff's claim was dismissed without the defendant having to present its defense.
For absolution from the instance to be refused at the close of the plaintiff's case, the plaintiff must adduce sufficient evidence upon which a reasonable court might or could find for the plaintiff. Where a plaintiff fails to establish that the defendant had any case to answer, absolution from the instance must be granted. In contract cases involving supply agreements, where: (1) the contract contains clauses disclaiming guarantee of availability and exempting liability for failure to supply (except for willful acts or negligence of staff); (2) the supplier made the product/service available but the consumer was prevented from accessing it by third parties; and (3) the consumer failed to take legal action against the third parties interfering with access, the supplier cannot be held liable for the consumer's losses. Furthermore, a plaintiff must lead adequate evidence to support a claim for damages; merely placing figures before the court without supporting evidence is insufficient to establish a damages claim.
The court expressed sympathy for the situation the plaintiff found himself in, acknowledging the difficult circumstances of being prevented from accessing water by A1 resettlement farmers. The court noted that even if it were to be generous to the plaintiff and allow the case to proceed, the plaintiff would still face a serious hurdle on the issue of damages due to the fundamental deficiencies in the evidence. The court observed that an agronomist's report from September 2010 had warned the plaintiff about low water levels and that alternative solutions (drawing water from Katanya Dam or Askala Dam) had been discussed but not pursued, though the court did not make a definitive finding on why these alternatives were not utilized. The court emphasized that rules of procedure should ensure justice is done between parties and should not be used to cause injustice, but noted this principle could not save a case where the plaintiff simply failed to establish any evidentiary basis for the claim.
This case is significant in Zimbabwean civil procedure law as it illustrates the application of the test for absolution from the instance at the close of the plaintiff's case. It reinforces the principle that a plaintiff must establish a prima facie case with sufficient evidence that requires rebuttal by the defendant. The case also demonstrates the importance of contractual exemption clauses in water supply agreements and clarifies that where a party's inability to perform arises from the actions of third parties rather than from the defendant's breach, and where contractual terms specifically disclaim liability for supply failures, the defendant cannot be held liable. The judgment emphasizes the necessity of leading adequate evidence to support claims for damages and the consequences of failing to do so. It also highlights that parties must take appropriate legal action (such as interdicts) against third parties who interfere with their contractual rights rather than seeking to hold the contracting party liable for third-party interference.