CaseNotes LogoCaseNotes
  • Home
  • Library
  • Research
  • Discussion Hub
  • Wiki
  • Latin Dictionary
  • Question Bank
  • Settings
S

Student

Student Account

South African Law • Jurisdictional Corpus
HomeLibraryResearchQuestionsSettings
Judicial Precedent
Ask AI

North West Provincial Department of Agriculture, Conservation, Environmental and Rural Development and Another v Bosigo Investment and Trading CC and Another

Citation(228/2024) [2025] ZASCA 191 (15 December 2025)
JurisdictionZA
Area of Law
Contract Law
Free account

Get the most out of this judgment

Create a free CaseNotes account to save this case, see how it's cited, get an AI summary, and search 10,000+ SA judgments.

Create free accountor sign in
Law of Damages
Administrative Law
Procurement Law

Facts of the Case

In July 2006, the North West Provincial Department of Agriculture issued a tender invitation for construction of large and small stock fencing on a rotational basis "as and when required" for 24 months. On 31 October 2006, Bosigo Investment and Trading CC and Keewave Trading 191 CC were jointly appointed as service providers for two years. The letter of appointment stated that it was not an official order and no work should be done until official orders were received. Annexure A listed various fencing projects totaling 926.2 km. During the first year, no orders were given. In the second year, Bosigo received orders for only four projects totaling 58.75 km. Bosigo discovered the Department had re-advertised the tender and awarded work to other service providers, including Selehogoa Trading CC which received an order for 36 km of fencing at Lower Majeakgoro (a project listed in Annexure A). Bosigo instituted action for breach of contract claiming damages of R18,793,629.66 based on alleged entitlement to all projects in Annexure A.

Legal Issues

  • Whether the contract entitled Bosigo to receive orders for all projects listed in Annexure A as a matter of course, or whether it was an order-based contract dependent on the Department's need
  • Whether the Department breached the contract by awarding work to other service providers
  • What is the proper method for calculating damages for loss of profit arising from breach of contract
  • What evidence must a plaintiff produce to prove saved expenses in a loss of profit claim
  • Whether the parties had agreed on the quantum of saved expenses

Judicial Outcome

1. The late filing of the notice of appeal, record of appeal and replying affidavit in the reinstatement application was condoned and the appeal reinstated. 2. The appeal was upheld with costs including those of two counsel. 3. The high court order was set aside and replaced with: "The plaintiff's claim is dismissed with costs including those of two counsel." 4. The cross-appeal was dismissed with costs including those of two counsel.

Ratio Decidendi

In a claim for contractual damages based on loss of profit, the plaintiff bears the onus to identify, quantify and prove all saved expenses that must be deducted from the contract price to establish actual damages. Comprehensive disclosure of operational costs through accounting records, audited financial statements, and detailed expenditure documentation is required as a minimum. Saved expenses cannot be presumed, estimated, or established through tender bid documents that were not intended to reflect actual operational costs for damages purposes. An agreement on a tender price is not an agreement on saved expenses for calculating loss of profit. Where a plaintiff fails to produce evidence of saved expenses despite having exclusive knowledge of and access to such information, damages have not been proved on a balance of probabilities and the claim must fail. Furthermore, a tender appointment expressed as being "as and when required" with an express stipulation that the appointment letter is "not an official order" creates an order-based contract dependent on need, not an automatic contractual entitlement to perform all work contemplated in the tender.

Obiter Dicta

The Court observed that the issue of whether Bosigo should have been awarded the orders that went to Selehogoa might be an administrative law issue involving considerations beyond pure contract law, but this was not the relief pursued in the action. The Court also noted that mora interest running from date of demand rather than date of judgment would mitigate any prejudice to the respondent from delays in prosecuting the appeal. On condonation applications, the Court reiterated that while an explanation for delay must be reasonable and cover the entire period, dilatory conduct by attorneys must be weighed against actual prejudice and prospects of success in the interests of justice.

Legal Significance

This case establishes important principles regarding the proof of damages in contractual claims for loss of profit, particularly in the public procurement context. It clarifies that: (1) the onus is strictly on the plaintiff to prove saved expenses with comprehensive documentary evidence; (2) tender documents listing material costs are not admissions of saved expenses for damages calculations; (3) courts will interpret "as and when required" language in tender awards as creating order-based contracts, not automatic entitlements to perform all listed work; (4) the comparative method for calculating contractual damages requires rigorous proof of the hypothetical position the plaintiff would have been in but for the breach; and (5) damages cannot be presumed or estimated but must be proved on a balance of probabilities with available evidence. The judgment reinforces the evidentiary burden on plaintiffs in commercial damages claims and provides guidance on contractual interpretation in government procurement matters.

Case relationship graph

Case Network

Explore 4 related cases • Click to navigate

Current Case
Related Case

Cases Cited in This Judgment

  • Capitec Bank Holdings Limited and Another v Coral Lagoon Investments 194 (Pty) Ltd and Others(470/2020) [2021] ZASCA 99 (09 July 2021)
    Applies

    Applied to establish that context and purpose may be used to elucidate the text of a contract, but are not a licence to contend for meanings unmoored in the…

  • Freddy Hirsch Group (Pty) Ltd v Chickenland (Pty) Ltd(20/10) [2011] ZASCA 22 (17 March 2011)
    Applies

    Applied to establish the principle that contractual damages compensate the innocent party by putting it in the position it would have occupied had the contract…

  • KPMG Chartered Accountants (SA) v Securefin Limited and Another(644/07) [2009] ZASCA 7 (13 March 2009)
    Applies

    Applied to establish that interpretation of a contract is a legal matter for the court and not a factual matter for witnesses.

  • Mbambisa and Others v Nelson Mandela Bay Metropolitan Municipality(272/2023) [2024] ZASCA 151 (8 November 2024)
    Applies

    Applied alongside Capitec Bank Holdings to reinforce the principle that context is used to elucidate text and not to impose meanings unmoored from the text and…

Practice This Case

Sign up to practise IRAC analysis, issue spotting, and argument building on this case.

  • Transnet Limited v Sechaba Photoscan (Pty) LtdCase No 98/03 (SCA) (Unreported, delivered 1 April 2004)
    Applies

    Applied to establish that contractual damages compensate for the difference between actual and hypothetical position after breach, provided this can be done by…

  • Willie Aaron Sibiya and Others v The Director of Public Prosecutions (Witwatersrand Local Division) and OthersCCT 45/04
    Applies

    Applied to establish that the starting point in interpreting a contract is its text, which must be construed contextually and with due regard to the purpose of…

  • Explore More Cases

    More Contract Law cases

    • (1) Douglas Tanyanyiwa (2) Douglas Warriors Football Club v Lawrence Bernard GwaradaCivil Appeal No. SC 150/11; Judgment No. SC 79/2014
    • (1) Elias Hwenga (2) Mercy Hwenga (3) Kenneth (4) Prince Nyemba (5) A. P. Phillip and Company (Private) Limited v FBC Bank LimitedJudgment No. SC 36/21, Civil Appeal No. SC 204/16
    • 68 Wolmarans Street Johannesburg (Pty) Ltd and Others v Tufh Limited(1263/2022) [2024] ZASCA 48 (15 April 2024)
    • A A Alloy Foundry (Pty) Limited v Titaco Projects (Pty) LimitedCase No. 309/97
    • A. Adam and Company (Private) Limited and Others v Goodliving Real Estate (Private) LimitedSC 18/21; Civil Appeal No. SC 444/19
    • Aaron Chitewe v Josiah ChiroodzaJudgment No. SC 70/2002, Civil Appeal No. 391/00
    • Aaron Majero v Dubekile DandaHH 119-18, CIV 'A' 311/08
    • Aaron Mwenje v Intermarket Building SocietySC. 80/05 (Civil Appeal No. 358/04)

    More South Africa cases

    • 3M South Africa (Pty) Ltd v The Commissioner for the South African Revenue Service(272/09) [2010] ZASCA 20 (23 March 2010)
    • 4 Seasons Logistics CC v Kgotse(1215/2023) [2026] ZASCA 09 (04 February 2026)
    • 4 Seasons Logistics CC v Nicholas Ngwanammoto Kgotse(1215/2023) [2026] ZASCA 09 (4 February 2026)
    • 4-Tune Investments (Pty) Ltd v Kingsgate Body CorporateCSOS 4565/WC/22 (Adjudication Order, 29 November 2023)
    • 68 Wolmarans Street Johannesburg (Pty) Ltd and Others v Tufh Limited(1263/2022) [2024] ZASCA 48 (15 April 2024)
    • 9 on Rydal Vale Court Body Corporate v Pan African Holdings Pty LtdCSOS-4563/KZN/23 (Adjudication Order, 8 November 2023)
    • AAA Investments (Proprietary) Limited v The Micro Finance Regulatory Council and Another
    2006 (11) BCLR 1255 (CC) (also reported as CCT 51/05)
  • A A Alloy Foundry (Pty) Limited v Titaco Projects (Pty) LimitedCase No. 309/97