Raydin Investments (respondent) entered into a principal building agreement with Bantry Construction Services (appellant) in March 2004 for the erection of a factory and offices in Linbro Park, Johannesburg. After completion and the architect's final certificate dated 7 December 2004, cracks developed in plasterwork and floor toppings. In August 2005, Raydin notified Bantry of the defects, attributing them to poor construction, which Bantry disputed. The dispute was referred to arbitration in accordance with Clause 40 of their agreement. Victor Booth, an engineer, was appointed arbitrator. The arbitration process was conducted under the summary rules of the Association of Arbitrators. After an in loco inspection on 27 July 2006 and later on 6 July 2007, and consideration of various reports, the arbitrator delivered an award on 3 August 2007 finding in favor of Raydin and ordering Bantry to pay R124,900 plus costs and interest. During the arbitration process, Bantry's attorney raised concerns about delays and alleged the arbitration had lapsed under section 23 of the Arbitration Act, and withdrew participation. When the award remained unsatisfied, Raydin approached the High Court to have the award made an order of court under section 31(1) of the Arbitration Act. Bantry opposed the application and belatedly launched a counter-application to set aside the award.
The appeal was dismissed with costs. The High Court judgment granting the relief sought (making the arbitration award an order of court) was upheld.
Where a party seeks to challenge an arbitration award, it must do so by way of a review application under section 33(1) of the Arbitration Act, either within the statutory six-week period from publication of the award or by launching a proper counter-application when an application is brought to make the award an order of court under section 31(1). A party cannot simply oppose an application to make an award an order of court as a means of challenging the substantive merits of the award. Parties who agree to arbitration waive their right to have the dispute relitigated, and the finality of arbitral awards must be respected unless proper statutory review proceedings are instituted. An arbitrator conducting an inspection in loco is not obliged to provide a separate report of observations to the parties; such observations form part of the arbitral process and should be reflected in the reasoned award. The burden of proof rests on the party alleging irregularity to establish what evidence the arbitrator improperly relied upon.
The Court noted somewhat critically that Bantry's case appeared to shift with the passage of time, and its contentions in the High Court amounted to no more than conclusions devoid of factual foundation. The Court observed that had Bantry properly launched a review application, the arbitrator could have entered the fray and defended himself against the allegations, instead of placing Raydin in the 'most invidious position' of having to defend the arbitrator's award on his behalf. The judgment implicitly criticizes the conduct of Bantry's attorney in raising procedural objections during the arbitration (such as alleging the arbitration had lapsed) and then withdrawing participation, only to later challenge the award through improper procedural means. While not strictly necessary for the decision, the Court's detailed recitation of the factual chronology appears designed to illustrate the extent of Bantry's shifting positions and procedural failures.
This case is significant in South African arbitration law for clarifying the proper procedure for challenging arbitration awards. It establishes that a party dissatisfied with an arbitration award cannot simply oppose an application to make the award an order of court under section 31(1) of the Arbitration Act. Instead, the dissatisfied party must proactively invoke the statutory review provisions under section 33(1) of the Act, either within six weeks of publication of the award or by launching a proper and timely counter-application for review. The judgment reinforces the principle that parties who agree to arbitration waive their right to have disputes relitigated and must respect the finality of arbitral awards unless proper review proceedings are instituted. It also clarifies that arbitrators conducting inspections in loco are not required to provide separate reports of their observations, as these form part of the arbitral process and will be reflected in the reasoned award. The case serves as a warning against adopting passive litigation strategies when challenging arbitration awards and emphasizes the importance of understanding and following correct procedural requirements.
Explore 1 related case • Click to navigate