During 21-28 February 1997, tropical cyclone Lizette severely damaged roads in Nampula Province, Mozambique, that the respondent contractor was about to hand over to the Mozambican Directorate of National Roads and Bridges. The contractor had an insurance policy with the appellant insurer covering fortuitous physical destruction or damage to the contract works, which comprised the opening of rural gravel roads and rehabilitation and construction of bridges. The damaged roads were low-cost, high-risk, high-maintenance, low-volume, all-weather roads designed to basic standards appropriate for emergency opening of roads after civil war. The contractor claimed R2.5 million for repair costs of 101.88 kilometres of damaged road works. The insurer repudiated the claim. Gildenhuys J in the Johannesburg High Court found the insurer liable and ordered payment of R2.5 million plus any VAT paid, but did not award interest. The insurer appealed, and the contractor cross-appealed on the interest issue.
1. The appeal was dismissed with costs, including costs of two counsel. 2. The cross-appeal succeeded with costs. The trial court order was amplified by insertion of paragraph (bbis): 'interest on the amount of R2 500 000 at the rate of 15.5% per annum is to be paid by the defendant as from 14 October 1997.'
1. An insured contractor has an insurable interest in repairing storm damage to contract works even where the works were designed by the employer, provided the damage was not caused solely by design defects but by a fortuitous event such as a cyclone. 2. A construction contract clause excepting the employer's design from the contractor's risk is intended to safeguard against costs of remedial work to defective design, not to exclude liability for fortuitous storm damage. 3. An insurer cannot rely on a policy exception for defective design without establishing: (a) what design standard is required, and (b) that the works fell below that standard. The insurer cannot demand a higher design standard than what the employer contracted and paid for. 4. Where parties settle quantum of damages, interest is not to be inferred as included in the settlement unless clearly stated. Agreement on a date of demand after settling quantum indicates the parties contemplated interest would run separately. 5. Under section 2A of the Prescribed Rate of Interest Act 55 of 1975, interest on an unliquidated debt runs from the date of written demand (if it sets out the claim sufficiently to enable reasonable assessment of quantum) or service of summons, whichever is earlier.
The Court noted that even if technological advances in road design and statistical flood return period calculations had been available for Nampula province, they would have been largely irrelevant to the rudimentary drainage structures that were all the employer could afford for this low-cost emergency road project. The Court also observed that the project was 'so unsophisticated and the funding so restricted' that the employer's resident engineer was obliged to design drainage works as construction progressed, using basic observational methods rather than sophisticated engineering calculations. The Court made reference to the purpose of such roads being described in a CSIR report as to 'get the people out of the mud', emphasizing the context-specific nature of design standards.
This case is significant in South African insurance law for clarifying the scope of insurable interest in construction contracts and the interpretation of policy exceptions for defective design. It establishes that storm damage to contract works is not excluded merely because works were designed by the employer rather than the contractor, where the damage was caused by a fortuitous event (cyclone) rather than solely by design defects. The case also confirms that an insurer cannot impose design standards higher than those contemplated by the parties to the construction contract, and must clearly establish what design standard is required before claiming a design was defective. On interest, it provides guidance on interpreting settlement agreements regarding quantum and the application of the Prescribed Rate of Interest Act to unliquidated debts in insurance claims. The judgment reinforces that interest claims are not lightly to be inferred as compromised when quantum is settled.